Ferndale-Ivy Area Street Improvements

Ferndale-Ivy Area Street Improvements, City Project 18-01, is a full street reconstruction project with construction scheduled for June-October 2019. The project includes many improvements to the neighborhood including the full removal of the existing street, the installation of new pavement, a new aggregate base and sand sub-base to support the road, and new concrete curb and gutter. Utility improvements include upgrades to the watermain system, sanitary sewer system, and the installation of a new storm sewer system. Concrete sidewalks are also proposed along Ivy Avenue and Ferndale Street to provide an off-street location for pedestrians.


Assessment Objection Form

Target Date  Actions
February 11, 2019 Accept Feasibility Study, Order Public Hearing, Authorize Preparation of Plans and Specifications
February 25, 2019 Public Hearing and Order Improvement
April 8, 2019 Approve Plans and Specifications, Authorize Advertisement for Bids, Authorize Preparation of Assessment Roll
April 22, 2019 Accept Assessment Roll and Order Assessment Hearings
May 9, 2019 Bid Opening
May 13, 2019 Assessment Hearing and Award of Contract
June 10, 2019 Adopt Revised Assessment Roll
June 2019 Begin Construction
November 2019 Assessments Certified to Ramsey County 
October 2019 Complete Construction