Project Status Update:

Utility repairs continue throughout the southern portion of the project (south of Minnehaha Avenue). Watermain has been replaced on all of Ferndale Street, Farrell Street south of Lion's Park, Fremont Avenue, and half of 5th Avenue. The remainder of the watermain on 5th Avenue will be completed by Friday, August 3rd. Early the week of August 6th the watermain work will shift to Farrell Street north of Lion's Park an then onto Margaret Avenue. 

The construction of the new road base has begun at the south end of Ferndale Street, working to the north. This work consists of removing 2 feet of the existing unstable soils and replacing them with a geotextile fabric overlain with 1-foot of free-draining sand and 8-inches of aggregate base. It is anticipated that the new road base will be complete on Ferndale Street around August 10th. The road base construction work will then shift to the east along Fremont, 5th, and Farrell Street.

The installation of concrete curb and gutter is planned to begin on Ferndale Street around August 16th. Please keep an eye on your door for flyers notifying you of curb installation around that time.

Overall the project is moving along well. A lot is happening in the neighborhood with our project, along with Xcel Energy's gas main replacement occurring simultaneously. Please continue to use caution when driving through the project area.

Thank you for your patience and cooperation as we work together on improving your neighborhood!

  1. Jon Jarosch

    Assistant City Engineer
    Phone: (651) 249-2405

Target Date Actions
August 23, 2017 Informational Packet Mailed
November 17, 2017 Neighborhood Meeting from 6:00PM - 7:00PM in Room C at the Maplewood Community Center
April 9, 2018 Council accepts Feasibility Report, Calls for Public Hearing and Authorizes Preparation of Plan and Specs
April 23, 2018 Council held Public Hearing and Ordered Improvements
May 14, 2018 Council Approved Plans, Authorized Ad for Bid, and Authorized Preparation of Assessment Role
May 29, 2018 Assessment Roll Accepted, Assessment Hearing Ordered
June 11, 2018 Assessment Roll Adopted, Contract Awarded to T.A. Schifsky and Sons
June 18, 2018 Construction Began in project area
November 16, 2018  Anticipated Project Completion
Location Map 17-18

Streets Impacted: 