Project Status Update:

Project Status Update: (7/22/2019)

The contractor is currently placing topsoil and sod along Mayhill Road and 7th Street. This work should be completed by the end of the week. Rainwater gardens along Mayhill Road will be installed this week as well. Once this work is completed, the final layer of asphalt will be installed on these roads.

The final layer of asphalt has been installed on all streets south of Minnehaha Avenue. Remaining work in this area includes the installation of plants in the Lion's Park rainwater garden and miscellaneous warranty repairs.

The construction of a sidewalk along the north side of Minnehaha Avenue, from Mary Street to Mayhill Road has begun. This sidewalk will be completed in the next couple of weeks.

Thank you for your patience and cooperation as we continue to work on improving your neighborhood!

  1. Jon Jarosch

    Assistant City Engineer
    Phone: (651) 249-2405

Target Date Actions
August 23, 2017 Informational Packet Mailed
November 17, 2017 Neighborhood Meeting from 6:00PM - 7:00PM in Room C at the Maplewood Community Center
April 9, 2018 Council accepts Feasibility Report, Calls for Public Hearing and Authorizes Preparation of Plan and Specs
April 23, 2018 Council held Public Hearing and Ordered Improvements
May 14, 2018 Council Approved Plans, Authorized Ad for Bid, and Authorized Preparation of Assessment Role
May 29, 2018 Assessment Roll Accepted, Assessment Hearing Ordered
June 11, 2018 Assessment Roll Adopted, Contract Awarded to T.A. Schifsky and Sons
June 18, 2018 Construction Began in project area
November 16, 2018  Anticipated Project Completion