Project Status Update:

Utility repairs and replacements are mostly complete in the portion of the project south of Minnehaha Avenue. Utility work remaining in this area includes the replacement of watermain along the Conway Service Drive and the installation of a large box-culvert near Lion's Park on Farrell Street. These items will be completed in the next 2-3 weeks. They are currently on hold until Xcel Energy completes their gas main replacements in the area. 

The construction of the new road base has shifted to Margaret Avenue. This work consists of removing 2 feet of the existing unstable soils and replacing them with a geotextile fabric overlain with 1-foot of free-draining sand and 8-inches of aggregate base. The road base has been completed on Ferndale Street and 5th Avenue.

The installation of concrete curb and gutter is complete on Ferndale Street. Curb installations are likely on 5th Avenue and Margaret Street the first week of September. Please keep an eye on your door for flyers notifying you of curb installation around that time.

Overall the project is moving along well. A lot is happening in the neighborhood with our project, along with Xcel Energy's gas main replacement occurring simultaneously. Please continue to use caution when driving through the project area.

Thank you for your patience and cooperation as we work together on improving your neighborhood!

  1. Jon Jarosch

    Assistant City Engineer
    Phone: (651) 249-2405

Target Date Actions
August 23, 2017 Informational Packet Mailed
November 17, 2017 Neighborhood Meeting from 6:00PM - 7:00PM in Room C at the Maplewood Community Center
April 9, 2018 Council accepts Feasibility Report, Calls for Public Hearing and Authorizes Preparation of Plan and Specs
April 23, 2018 Council held Public Hearing and Ordered Improvements
May 14, 2018 Council Approved Plans, Authorized Ad for Bid, and Authorized Preparation of Assessment Role
May 29, 2018 Assessment Roll Accepted, Assessment Hearing Ordered
June 11, 2018 Assessment Roll Adopted, Contract Awarded to T.A. Schifsky and Sons
June 18, 2018 Construction Began in project area
November 16, 2018  Anticipated Project Completion