Londin-Highpoint Area Pavement Rehabilitation

The Londin-Highpoint project has been completed. The Contractor, Park Construction Company, completed project improvements in late July. The Contractor will be coming back in the fall of 2018 to repair some minor items and ensure that grass has established in disturbed boulevard areas. City staff will also perform a spring 2019 inspection of the area to identify any warranty related repairs. In the meantime, if you have any questions or concerns with the project, please contact us at your earliest convenience. Enjoy the smooth roads!

This project included the full-depth reclamation (grinding) of the project streets, the replacement of severely deteriorate concrete curb and gutter, and the installation of 2 new layers of bituminous pavement.

  1. Jon Jarosch

    Assistant City Engineer
    Phone: (651) 249-2405

Proposed Timeline

Target Dates Actions
September 12, 2017 Project Information Packet Mailed
November 14, 2017 Neighborhood Meeting from 6:00PM - 7:30PM in Room B at the Maplewood Community Center
February 12, 2018 Council accepts Feasibility Report, Calls for Public Hearing and Authorizes Preparation of Plan and Specs
March 12, 2018 Council held Public Hearing and Ordered Improvement
April 9, 2018 Council Approved Plans, Authorized Ad for Bid, and Authorized Preparation of Assessment Role
April 23, 2018 Council Accepted Assessment Roll and Ordered Assessment Hearing
May 4, 2018 Bid Opening
June 2018 Construction Began in Project Area
July 2018 Project Improvements Completed
Spring 2019 City staff perform warranty walk-through of project
Location Map 17-19

Streets Impacted:

Crestview Drive, Highpoint Curve, King Avenue, Londin Lane, Marnie Street, Pond Avenue